Windows Secondary Glazing Low Cill Provide and fit secondary glazing to the windows in the rooms listed below: X X X X The secondary windows should be constructed as to ensure that they match the style of the existing windows and so th 2023-11-05 Standard Clauses For Housing Act Use - HHSRS > 2 - Excess Cold #excess_cold
Windows Secondary Glazing Normal Cill Secondary glazing clause (Ordinary cill height version) Provide and fit secondary glazing to the windows in the rooms listed below: X X X X The secondary windows should be constructed as to ensure tha 2023-11-05 Standard Clauses For Housing Act Use - HHSRS > 2 - Excess Cold #excess_cold
Windows Overhaul Full Overhaul windows Overhaul the double hung sash window/s to the XXX, cut out and renew all rotten or badly worn timbers to the sashes, frame and cill. The finished sashes and other parts of the wi 2023-11-05 Standard Clauses For Housing Act Use - HHSRS > 2 - Excess Cold #excess_cold
Windows Timber Sashes Replace timber sashes but retain frame Take out the defective window sashes to the XXX. Provide and hang new sashes to match original, properly glazed. Cut out and renew any rotten timber to frame and 2023-11-05 Standard Clauses For Housing Act Use - HHSRS > 2 - Excess Cold #excess_cold
Window Sill Lintel Provide and fix new stone sill and new steel or reinforced concrete lintel. Provide and fit new $ timber double-glazed timber windows to match as far as possible the current design, which will achieve 2023-11-05 Standard Clauses For Housing Act Use - HHSRS > 2 - Excess Cold #excess_cold
Window Timber Sash Timber sash window Take out the existing window sashes and frames, listed below and suitably dispose of: X X X X Provide and fit new $ timber double-glazed timber windows to match as far as possible t 2023-11-05 Standard Clauses For Housing Act Use - HHSRS > 2 - Excess Cold #excess_cold
Wall Insulation Cavity Cavity Wall Insulation Employ a registered contractor to carry out a pre-installation assessment of the property to determine its suitability for cavity insulation. If the brickwork and cavity are sui 2023-11-05 Standard Clauses For Housing Act Use - HHSRS > 2 - Excess Cold #excess_cold
Walls Insulation Basement To the following walls: XXX Remove all skirting, picture rails, coving, radiators, pipework, electrical fittings, wiring and other features to enable the fixing of insulation to the entire internal su 2023-11-05 Standard Clauses For Housing Act Use - HHSRS > 2 - Excess Cold #excess_cold
Walls Insulation Fixed Provide insulation to the internal faces of the external wall(s) to the XXX room. The insulation provided shall be attached to the walls in accordance with the manufacturer’s guidance and be designed 2023-11-05 Standard Clauses For Housing Act Use - HHSRS > 2 - Excess Cold #excess_cold
Walls Insulation Solid Brickwork Prepare the internal faces of the XXX external facing walls and window reveals to receive wall insulation: Remove all skirting, picture rails, coving, radiators, pipework, electrical fittings, wiring 2023-11-05 Standard Clauses For Housing Act Use - HHSRS > 2 - Excess Cold #excess_cold